Skip to main content
09-2010-1570Administrative - FormalFinal Order IssuedFY 2010· Region 09

EPA v. 402 ADOT State Route 179 Oak Creek FY10 AO (PCS AZS000018)

Case summary

AO directed ADOT to install BMPs along the Oak Creek Bridge and to develop and implement BMPs to control sediment-laden stormwater pumped from the creek area. EPA also issued a concurrent AO to Fisher Sand and Gravel, ADOT's general contractor.

Defendants (1)

  • Arizona Dept of TransportationNamed in settlement

Facilities (1)

  • ADOT STATE ROUTE 179 OAK CREEK

    STATE ROUTE 179 BETWEEN MP304.53 AND 310.41, SEDONA, AZ, 85351

    Registry ID: 110041220363

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • 402/404 ADOT State Route 179 Oak Creek FY10 AOentered 2010-03-11

    Primary law: CWA

Timeline (2 milestones)

  • 2010-03-11Final Order Issued
  • 2010-03-22Enforcement Action Data Entered

Case metadata

EPA activity ID
1800084033
Case number
09-2010-1570
Lead agency
EPA
EPA region
09
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 09-2010-1570 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.