EPA v. GTE Government Systems
Unilateral Administrative Order Without Adjudication
Case summary
This is a UAO pursuant to CERCLA 106 issued to GTE Corporation. This order was originally issued to Verizon Communications as occupant of a facility known as the GTE Government Systems site. The name of the Respondent was changed to GTE Corporation, instead of Verizon, when all parties acknowledged that this was the appropriate legal successor corporation to GTE Government Systems. The order directs a time-critical removal action consisting of installation of a sub-slab depressurization system at a home impacted by vapor intrusion of TCE from groundwater contamination at the former GTE Government Systems facility.
Defendants (1)
- GTE CorporationNamed in complaintNamed in settlement
Facilities (1)
GTE GOVERNMENT SYSTEMS CORPORATION
100 FERGUSON DR, MOUNTAIN VIEW, CA, 94039
Registry ID: 110013847597
Statutes cited
- CERCLA 107A — Cost Recovery
- CERCLA 106A — Imminent & Substantial Endangerment Order
Enforcement conclusions (1)
GTE Government Systems UAOentered 2003-02-06
Primary law: CERCLA
Timeline (4 milestones)
- 2003-02-06Complaint Filed/Proposed Order
- 2003-02-06Final Order Issued
- 2003-03-27Enforcement Action Closed
- 2003-03-27Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 93255
- Case number
- 09-2003-0024
- Lead agency
- EPA
- EPA region
- 09
- Primary statute
- Cost Recovery
Sourced verbatim from EPA ECHO Enforcement Case Report for case 09-2003-0024 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.