09-1998-0110JudicialFinal Order EnteredFY 1998· Region 09

EPA v. KUSHWOOD MANUFACTURING

Default Order With Penalty

Case summary

KUSHWOOD VIOLATED THE SIP APPROVED NEW SOURCE REVIEW PROGRAM BY CONSTRUCTING THE FACILITY IN ONTARIO, CA WITHOUT OBTAINING A PERMIT TO CONSTRUCT OR COMPLYING WITH LOWEST ACHIEVEABLE EMISSION REDUCTION. KUSHWOOD NEEDS TO GET PERMIST AND INSTALL/APPROVE LAER.

Defendants (1)

  • KUSHWOOD MANUFACTURING INC.Named in complaintNamed in settlement

Facilities (1)

  • KUSHWOOD MFG INC

    2560 E PHILADELPHIA ST, ONTARIO, CA, 917617768

    Registry ID: 110000478199

Statutes cited

  • CAA 110Implementation Plan for National Primary and Secondary Ambient Air Quality Standards

Enforcement conclusions (1)

  • KUSHWOOD MANUFACTURING (Default Order)entered 2006-05-08

    Primary law: CAA

    Federal penalty: $190,000

Timeline (5 milestones)

  • 1998-09-30Referred To Dept Of Justice
  • 1998-10-14Enforcement Action Data Entered
  • 2000-03-01Complaint Filed With Court
  • 2006-05-08Final Order Entered
  • 2006-05-08Final Order Lodged

Case metadata

EPA activity ID
52986
Case number
09-1998-0110
Lead agency
EPA
HQ division
AIR
Branch
ORC2
EPA region
09
Multimedia
No
Voluntary self-disclosure
No
Primary statute
Implementation Plan for National Primary and Secondary Ambient Air Quality Standards