EPA v. UNIVERSITY COGENERATION, INC.
Final Order With Penalty
Penalty assessed
$25,000
Case summary
UNIVERSITY OWNS AND OPERATES A COGENERATION SYSTEM AT ITS BERRY HOLDING COMPANY OPERATIONS. THE FACILITY CON- SISTS OF A GAS TURBINE AND A WASTE HEAT BOILER FIRED BY DUCT BURNERS. PURSUANT TO THE NEW SOURCE PERFORMANCE STANDARDS, UNIVERSITY IS REQUIRED TO NOTIFY EPA OF CONSTRUC- TION, AND STARTUP, AND TO PERFORM CERTAIN EMISSIONS TEST. UNIVERSITY DID NOT PROVIDE SOME OF THE REQUIRED NOTIFICATION AND ALSO DID NOT PERFORM EMISSIONS TEST ON THE DUCT BURNERS.
Defendants (3)
- BERRY HOLDING COMPANY PROPERTY
- LITTLE SIGNAL HILLS
- UNIVERSITY COGENERATIONNamed in complaintNamed in settlement
Facilities (2)
UNIVERSITY COGENERATION INCORPORATED
LITTLE SIGNAL HILLS S28 T12N R24W, BAKERSFIELD, CA, 93308
Registry ID: 110010676152
UNIVERSITY COGENERATION INCORPORATED
LITTLE SIGNAL HILLS S28 T12N R24W, BAKERSFIELD, CA, 93308
Registry ID: 110010676152
Statutes cited
- CAA 111 — New Source Performance Standards
Enforcement conclusions (1)
UNIVERSITY COGENERATION PARTN.entered 1989-09-26
Primary law: CAA
Federal penalty: $25,000
Timeline (8 milestones)
- 1988-09-30PRN Sent
- 1989-04-03Referred To Dept Of Justice
- 1989-05-16Referred TO U.S. Attorney
- 1989-05-30Complaint Filed With Court
- 1989-09-26Final Order Lodged
- 1989-09-26Final Order Entered
- 1989-09-26Concluded
- 1991-04-30Enforcement Action Closed
Case metadata
- EPA activity ID
- 52151
- Case number
- 09-1988-0025
- Lead agency
- EPA
- HQ division
- AIR
- Branch
- AIR
- EPA region
- 09
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- New Source Performance Standards