Skip to main content
08-2025-0045Administrative - FormalClosedFY 2025· Region 08

EPA v. CITY OF HARDIN MTDW0005I ESA

Final Order With Penalty

Case summary

On March 26, 2025, Region 8 issued and Expedited Settlement Agreement (ESA) to the City of Hardin Water Treatment Plant to address violations of their NPDES permit requirements by failing to submit monthly discharge monitoring reports within required timeframes and failing to complete weekly inspections of the backwash pond dike walls. Under the Consent Agreement, the City of Hardin has agreed to pay a civil administrative penalty of $1,320 to resolve its federal civil penalty liability for these alleged violations. The City of Hardin has corrected all deficiencies identified by the EPA.

Defendants (1)

  • City of HardinNamed in complaintNamed in settlement

Facilities (1)

  • HARDIN, CITY OF

    406 N. CHEYENNE AVENUE, HARDIN, MT, 59034

    Registry ID: 110039892541

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • CITY OF HARDIN MTDW0005I ESAentered 2025-03-26

    Primary law: CWA

    Federal penalty: $1,320

Timeline (5 milestones)

  • 2025-03-26Final Order Issued
  • 2025-03-26Complaint Filed/Proposed Order
  • 2025-04-09Enforcement Action Data Entered
  • 2025-07-14NPDES Closed
  • 2025-07-14Enforcement Action Closed

Case metadata

EPA activity ID
3604357176
Case number
08-2025-0045
Lead agency
EPA
EPA region
08
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations