EPA v. Administrative Settlement Prospective Purchaser (Idaho Pole Company Site)
Case summary
This Administrative Settlement Agreement for Removal Action and Payment of Response Costs by Prospective Purchaser (Settlement) is entered into voluntarily by and between the United States on behalf of the Environmental Protection Agency (EPA), the State of Montana (?State?) through the Montana Department of Environmental Quality (DEQ), and the prospective purchaser, Scout DAC, LLC (Purchaser). This Settlement provides for the performance of a removal action by Purchaser and the payment of certain response costs incurred by the United States at or in connection with the property located at Cedar Street, Bozeman, Montana 59715 near the northern limits of Bozeman, Montana, in the east half of Section 6 and the west half of Section 5, and the north half of Section 8, Township 2 South, Range 6E of Gallatin County (the ?Property?), which is part of the Idaho Pole Co. Superfund Site (Site) in Bozeman, Montana.
Defendants (1)
- Scout DAC, LLC.Named in complaintNamed in settlement
Facilities (1)
IDAHO POLE CO.
CEDAR ST, BOZEMAN, MT, 59715
Registry ID: 110071101418
Statutes cited
- CERCLA 122H — Administrative Cost Recovery Settlement
Enforcement conclusions (1)
Administrative Settlement Prospective Purchaser (Idaho Pole Company Site)entered 2022-06-30
Primary law: CERCLA
Timeline (2 milestones)
- 2022-06-30Final Order Issued
- 2022-10-05Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3603374142
- Case number
- 08-2022-0129
- Lead agency
- EPA
- EPA region
- 08
- Voluntary self-disclosure
- No
- Primary statute
- Administrative Cost Recovery Settlement
Sourced verbatim from EPA ECHO Enforcement Case Report for case 08-2022-0129 . Bulk data: ICIS-FEC download summary.