EPA v. PSCO Comanche Station
Final Order With Penalty
Case summary
Respondent did not meet coal combustion residual (CCR) regulation requirements in 40 CFR 257. Specifically, the facility failed to install an adequate groundwater monitoring system; failed to develop and submit annual groundwater monitoring and corrective action reports; failed to statistical analysis and establish background; failed to conduct semi-annual monitoring; exceeded the cease-receipt date for non-compliant surface impoundment; failed to post on information on public website, maintain information in facility operating record, and failed to provided notifications to state. The Consent Agreement included payment of a penalty on 6/16/22 and implementation of measures to return the facility to compliance with the CCR regulations.
Defendants (1)
- PSCO Comanche StationNamed in complaintNamed in settlement
Facilities (3)
COMANCHE (470)
2005 LIME RD, PUEBLO, CO, 81006
Registry ID: 110000467851
COMANCHE (470)
2005 LIME RD, PUEBLO, CO, 81006
Registry ID: 110000467851
COMANCHE (470)
2005 LIME RD, PUEBLO, CO, 81006
Registry ID: 110000467851
Statutes cited
- RCRA 3008A — Compliance Order: Injunctive & Penalty
Enforcement conclusions (1)
PSCO Comanche Stationentered 2022-05-20
Primary law: RCRA
Federal penalty: $925,000
Timeline (4 milestones)
- 2022-05-20Complaint Filed/Proposed Order
- 2022-05-20Final Order Issued
- 2022-07-05Enforcement Action Closed
- 2022-09-16Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3603356110
- Case number
- 08-2022-0117
- Lead agency
- EPA
- EPA region
- 08
- Voluntary self-disclosure
- No
- Primary statute
- Compliance Order: Injunctive & Penalty
Sourced verbatim from EPA ECHO Enforcement Case Report for case 08-2022-0117 . Bulk data: ICIS-FEC download summary.