08-2019-0127Administrative - FormalClosedFY 2019· Region 08

EPA v. BOULDER RIVER FOUNDRY

Final Order No Penalty

Case summary

Facility conducts a metal molding and casting that is subject to categorical pretreatment standards. The facility has changed the process and no longer discharges to the POTW. The administrative order on consent (AOC) requires the facility to cease discharge, and to comply with the CWA and pretreatment regulations for any future discharges of wastewater.

Defendants (1)

  • Boulder River FoundryNamed in complaintNamed in settlement

Facilities (1)

  • BOULDER RIVER FOUNDRY

    201 CENTENNIAL DRIVE, BIG TIMBER, MT, 59011

    Registry ID: 110069341849

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • BOULDER RIVER FOUNDRYentered 2019-09-26

    Primary law: CWA

Timeline (4 milestones)

  • 2019-09-26Final Order Issued
  • 2019-09-30Enforcement Action Data Entered
  • 2020-01-28NPDES Closed
  • 2020-01-28Enforcement Action Closed

Case metadata

EPA activity ID
3601987290
Case number
08-2019-0127
Lead agency
EPA
EPA region
08
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations