EPA v. ALAN KRUCKENBERG
Final Order With Penalty
Case summary
The EPA Region 8 NPDES Enforcement Team within ECEJ has settled a Combined Complaint and Consent Agreement with Alan Kruckenberg Construction, Inc., for failing to obtain and to maintain a stormwater permit for the construction activities in the housing development known as On the Hill in Millcreek, Utah. SWPPP deficiencies were identified in the inspection report. No response was received at that time. AKC was sent an Administrative Order for Compliance on June 18, 2013, and the documents were then sent to the EPA by AKC. Subsequent tot he Order, the EPA and Respondent entered into a Combined Complaint and Consent Agreement (CCCA), for which the Final Order was issued December 16, 2014. In the CCCA, Respondent agrees to pay a penalty
Defendants (1)
- ALAN KRUCKENBERGNamed in complaintNamed in settlement
Facilities (1)
ALAN KRUCKENBERG CONSTRUCTION-ARCADIA HOME SITE
2940 EAST 3300 SOUTH, MILLCREEK, UT, 84109
Registry ID: 110056148431
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
ALAN KRUCKENBERGentered 2014-12-16
Primary law: CWA
Federal penalty: $27,000
Timeline (4 milestones)
- 2014-10-09Enforcement Action Data Entered
- 2014-12-16Final Order Issued
- 2014-12-16Complaint Filed/Proposed Order
- 2017-02-15Enforcement Action Closed
Case metadata
- EPA activity ID
- 3400298102
- Case number
- 08-2014-0138
- Lead agency
- EPA
- EPA region
- 08
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit