EPA v. TOWN OF EATON AKA EATON BEETS
Final Order With Specified Cost Recovery
Case summary
The EPA identified about 138,000 square feet of asbestos containing materials in these structures with asbestos concentrations inside exceeding 1%. Much of the asbestos materials on or in the buildings had migrated outside, caused in part by continued trespass, attempts by owners to reclaim scrap metal inside the buildings, and by animal infestation. The EPA issued an Action Memorandum for cleanup of asbestos contamination at the Property on April28, 2011, and requests for ceiling increases on March 16, 2012 and August 31, 2012. The EPA began removal work at the Property on April 28, 2011 and completed this work in April of 2013
Defendants (1)
- TOWN OF EATONNamed in complaintNamed in settlement
Facilities (1)
EATON SUGAR BEET FACTORY
US HWY 85 & EAST COLLINS STREET, EATON, CO, 80615
Registry ID: 110042267329
Statutes cited
- CERCLA 107L — Lien
Enforcement conclusions (1)
TOWN OF EATONentered 2014-06-26
Primary law: CERCLA
Timeline (4 milestones)
- 2013-06-26Complaint Filed/Proposed Order
- 2014-06-26Final Order Issued
- 2014-09-12Enforcement Action Data Entered
- 2014-10-23Enforcement Action Closed
Case metadata
- EPA activity ID
- 3400285971
- Case number
- 08-2014-0095
- Lead agency
- EPA
- EPA region
- 08
- Voluntary self-disclosure
- No
- Primary statute
- Lien
Sourced verbatim from EPA ECHO Enforcement Case Report for case 08-2014-0095 . Bulk data: ICIS-FEC download summary.