Skip to main content
08-2013-0004Administrative - FormalFinal Order IssuedFY 2013· Region 08

EPA v. LYNN BUTTARS

Final Order No Penalty

Case summary

The Corps conducted a Site inspection on September 30, 2011, and observed that the historic channel of Clarkston Creek, as well as adjacent wetlands visible in a 2006 aerial photo, had been completely filled with unauthorized discharges of dredged and fill material and graded. The Corps further observed that Clarkson Creek had been straightened and channelized at the Site. On January 9, 2012, the Corps referred this case to the EPA for enforcement in accordance with the Memorandwn of Agreement Between the Department of the Army and the Envirorunental Protection Agency Concerning Federal Enforcement of the Section 404 Program of the Clean Water Act, dated January 19, 1989.

Defendants (1)

  • LYNN BUTTARSNamed in complaintNamed in settlement

Facilities (1)

  • MR LYNN BUTTARS

    127 NORTH MAIN / PO BOX 64, CLARKSTON, UT, 84305

    Registry ID: 110054926835

Statutes cited

  • CWA 301NPDES Discharge without a Permit
  • CWA 404Permits for Dredge and Fill Material

Enforcement conclusions (1)

  • LYNN BUTTARSentered 2012-10-30

    Primary law: CWA

Timeline (2 milestones)

  • 2012-10-30Final Order Issued
  • 2013-01-25Enforcement Action Data Entered

Case metadata

EPA activity ID
3400042696
Case number
08-2013-0004
Lead agency
EPA
EPA region
08
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit

Sourced verbatim from EPA ECHO Enforcement Case Report for case 08-2013-0004 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.