08-2012-0012Administrative - FormalFinal Order IssuedFY 2012· Region 08

EPA v. OPHIR MILLS AND SMELTER SITE

Final Order With Specified Cost Recovery

Case summary

THIS SETTLEMENT AGREEMENT CONCERNS THE OPHIR MILLS AND SMELTER SUPERFUND SITE LOCATED IN OPHIR, TOOLE COUNTY, UTAH. IN RESPONSE TO THE RELEASE OR THREATENED RELEASE OF HAZARDOUS SUBSTANCES AT OR FROM THE SITE. EPA TOOK RESPONSE ACTIONS AT THE SITE. THE REMOVAL ACTION FOCUSED ON REMOVING CONTAMINANTS FROM PAST MINING ACTIVITIES IN AND AROUND THE TOWN OF OPHIR. IN PERFORMING RESPONSE ACTIONS AT THE SITE, EPA HAS INCURRED RESPONSE COSTS AT OR IN CONNECTION WITH THE SITE. EPA ALLEGES THE SETTLING PARTY IS THE RESPONSIBLE PARTY AND IS LIABLE FOR RESPONSE COSTS INCURRED OR TO BE INCURRED AT OR IN CONNECTION WITH THE SITE.

Defendants (1)

  • ATLANTIC RICHFIELD COMANYNamed in complaintNamed in settlement

Facilities (1)

  • OPHIR MILLS AND SMELTER

    TOWNSHIP SECTION 23 T5S-R4W, OPHIR, UT, 84071

    Registry ID: 110009314562

Statutes cited

  • CERCLA 104E3Entry Access
  • CERCLA 106AImminent & Substantial Endangerment Order
  • CERCLA 122HAdministrative Cost Recovery Settlement
  • CERCLA 107ACost Recovery

Enforcement conclusions (1)

  • OPHIR MILLS AND SMELTER SITEentered 2011-12-01

    Primary law: CERCLA

Timeline (2 milestones)

  • 2011-12-01Final Order Issued
  • 2011-12-16Enforcement Action Data Entered

Case metadata

EPA activity ID
2600082221
Case number
08-2012-0012
Lead agency
EPA
EPA region
08
Voluntary self-disclosure
No
Primary statute
Entry Access

Sourced verbatim from EPA ECHO Enforcement Case Report for case 08-2012-0012 . Bulk data: ICIS-FEC download summary.