08-2008-0266Administrative - FormalClosedFY 2008· Region 08

EPA v. Industrial Builders

Final Order With Penalty

Case summary

The Adminisrative Complaint and Notice of Opportunity for Hearing is issued to Industrial Builders for the unauthorized discharge of dredged and/or fill material into the Heart River and its adjacent wetlands.

Defendants (1)

  • Industrial BuildersNamed in complaint

Facilities (1)

  • INDUSTRIAL BUILDERS INC

    1307 COUNTY ROAD 17 NORTH, WEST FARGO, ND, 58078

    Registry ID: 110006072409

Statutes cited

  • CWA 404Permits for Dredge and Fill Material

Enforcement conclusions (1)

  • Industrial Buildersentered 2009-01-22

    Primary law: CWA

    Federal penalty: $8,690

Timeline (4 milestones)

  • 2008-09-30Complaint Filed/Proposed Order
  • 2008-10-01Enforcement Action Data Entered
  • 2009-01-22Final Order Issued
  • 2009-04-24Enforcement Action Closed

Case metadata

EPA activity ID
1400009977
Case number
08-2008-0266
Lead agency
EPA
EPA region
08
Voluntary self-disclosure
No
Primary statute
Permits for Dredge and Fill Material