EPA v. Braden-Deem, Inc.
Final Order With Penalty
Case summary
This expedited consent agreement is issued to Braden-Deem, Inc. for the unauthorized discharge of an undetermined amount of oil into an unnamed wetland that flows into Cooper Creek, which is a tributary to Cooper Lake. Respondent also admits that they failed to prepare and implement a Spill, Prevention, Control and Countermeasures (SPCC) Plan for it's Cooper Cove Muddy-Dakota Battery No. 1 facility.
Defendants (1)
- Braden-Deem, Inc.Named in complaint
Facilities (1)
BRADEN-DEEM, INC.
LAT. 41 DEG. 31; 9 N, LONG. 106 DEG. 4' 9 W, LARAMIE, WY, 82070
Registry ID: 110024273766
Statutes cited
- CWA 311J — SPCC and/or Federal Response Plan Violations
- CWA 311B — Oil & Hazardous Substances Discharge
Enforcement conclusions (1)
Braden-Deem, Inc.entered 2006-06-02
Primary law: CWA
Federal penalty: $2,450
Timeline (3 milestones)
- 2006-06-02Final Order Issued
- 2006-06-02Complaint Filed/Proposed Order
- 2006-06-29Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 200000575
- Case number
- 08-2006-0110
- Lead agency
- EPA
- EPA region
- 08
- Voluntary self-disclosure
- No
- Primary statute
- SPCC and/or Federal Response Plan Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 08-2006-0110 . Bulk data: ICIS-FEC download summary.