08-2003-0173Administrative - FormalClosedFY 2003· Region 08
EPA v. Riley Lane Residence Site
Final Order With Specified Cost Recovery
Case summary
This Agreement for Recovery of Past Response Costs is entered into by EPA and the Union Pacific Railroad for a past time-critical removal response action taken by EPA at the Riley Lane Residence Site.
Defendants (1)
- Union Pacific RailroadNamed in complaintNamed in settlement
Facilities (1)
RILEY LANE RESIDENCES
5390 S RILEY LANE, MURRAY, UT, 841070000
Registry ID: 110002156041
Statutes cited
- CERCLA 122H — Administrative Cost Recovery Settlement
Enforcement conclusions (1)
Riley Lane Residence Siteentered 2003-07-17
Primary law: CERCLA
Timeline (5 milestones)
- 2003-07-17Final Order Issued
- 2003-07-17Complaint Filed/Proposed Order
- 2003-09-02Enforcement Action Data Entered
- 2008-03-12Enforcement Action Closed
- 2008-03-12Pipeline Closed
Case metadata
- EPA activity ID
- 102095
- Case number
- 08-2003-0173
- Lead agency
- EPA
- EPA region
- 08
- Primary statute
- Administrative Cost Recovery Settlement
Sourced verbatim from EPA ECHO Enforcement Case Report for case 08-2003-0173 . Bulk data: ICIS-FEC download summary.