Case summary

This expedited consent agreement is issued to Sweetman Construction Company for failure to prepare and implement a facility SPCC Plan. The deficiencies include: management approval not evidenced in the Plan; Plan not reviewed every three years; tank integrity testing not addressed; prompt correction of oil leaks not addressed; and written tank inspection procedures not appropriate for the facility.

Defendants (1)

  • G. P. SweetmanNamed in complaintNamed in settlement

Facilities (1)

  • SWEETMAN CONST CO

    3000 WEST MADISON, SIOUX FALLS, SD, 57104

    Registry ID: 110064115087

Statutes cited

  • CWA 311JSPCC and/or Federal Response Plan Violations

Enforcement conclusions (1)

  • Sweetman Construction Companyentered 2002-11-15

    Primary law: CWA

    Federal penalty: $800

Timeline (3 milestones)

  • 2002-11-15Complaint Filed/Proposed Order
  • 2002-11-15Final Order Issued
  • 2002-11-21Enforcement Action Data Entered

Case metadata

EPA activity ID
88812
Case number
08-2003-0009
Lead agency
EPA
EPA region
08
Voluntary self-disclosure
No
Primary statute
SPCC and/or Federal Response Plan Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 08-2003-0009 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.