Skip to main content
08-2001-0102Administrative - FormalClosedFY 2001· Region 08

EPA v. SPRING GROVE RESOURCE RECOVERY, INC.

Final Order With Penalty

Penalty assessed

$8,149

Case summary

THIS CONSENT AGREEMENT/FINAL ORDER IS ISSUED TO SPRING GROVE RESOURCE RECOVERY, FOR FAILURE TO SUBMIT AN EXCEPTION REPORT FOR ANY HAZARDOUS WASTE SHIPMENT FOR WHICH THE GENERATOR HAS NOT RECEIVED A COPY OF THE MANIFEST SIGNED BY THE DESIGNATED FACILITY WITHIN THE NUMBER OF DAYS OF SHIPMENT SPECIFIED IN REGULATIONS. RESPONENT'S FAILURE TO COMPLY WITH THE REQUIREMENT CONSTITUTES 33 VIOLATIONS OF THE REGULATIONS. THIS ORDER IS SUBJECT TO THE 22 RULE WHICH IS ENTERED INTO BY THE PARTIES FOR THE PURPOSE OF SIMULTANEOUSLY COMMENCING AND CONCLUDING THIS MATTER. THE ASSESSED PENALTY FOR THE STATED VIOLATIONS IS $8,149.

Defendants (1)

  • SPRING GROVE RESOURCE RECOVERY, INC.Named in complaintNamed in settlement

Facilities (1)

  • SPRING GROVE RESOURCE RECOVERY INCORPORATED

    4879 SPRING GROVE AVENUE, CINCINNATI, OH, 45232

    Registry ID: 110000544206

Statutes cited

  • RCRA 3008ACompliance Order: Injunctive & Penalty

Enforcement conclusions (1)

  • SPRING GROVE RESOURCE RECOVERY, INC.entered 2001-07-23

    Primary law: RCRA

    Federal penalty: $8,149

Timeline (4 milestones)

  • 2001-07-23Complaint Filed/Proposed Order
  • 2001-07-23Final Order Issued
  • 2001-08-10Enforcement Action Data Entered
  • 2001-08-16Enforcement Action Closed

Case metadata

EPA activity ID
51812
Case number
08-2001-0102
Lead agency
EPA
HQ division
RCR
EPA region
08
Multimedia
No
Voluntary self-disclosure
No
Primary statute
Compliance Order: Injunctive & Penalty

Sourced verbatim from EPA ECHO Enforcement Case Report for case 08-2001-0102 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.