EPA v. R.W. DAVIS CONSTRUCTION, INC.
Case summary
THIS REFERRAL REQUESTS DOJ TAKEN ACTION AGAINST R.W. DAVIS AND R.W. DAVIS CONSTRUCTION, INC. FOR UNAUTHORIZED DISCHARGES INTO UTAH LAKE, A WATER OF THE US. THE VIOLATIONS INCLUDE FAILURE TO COMPLY WITH THE CONDITIONS OF NATIONWIDE PERMIT 3, DISCHARGE OF DREDGE AND FILL MATERIAL WITH AN AUTHORIZED 404 PERMIT, AND VIOLATIONS FOR FAILURE TO RESPOND TO AN INFORMATION REQUEST. THE REGION DOES NOT YET HAVE ALL THE NECESSARY INFORMATION TO CALCULATE A PENALTY IN THIS CASE. THEREFORE, THE REGION IS NOT RECOMMENDING A BOTTOM LINE PENALTY AT THIS TIME.
Defendants (1)
- RICHARD W. DAVISNamed in complaintNamed in settlement
Facilities (1)
R.W. DAVIS CONSTRUCTION, INC.
1483 E SPRINGDELL DR, PROVO, UT, 84604
Registry ID: 110012371012
Statutes cited
- CWA 309 — Violation of Existing AO
- CWA 404 — Permits for Dredge and Fill Material
Enforcement conclusions (1)
R.W. DAVIS CONSTRUCTION, INC.entered 2005-02-15
Primary law: CWA
Timeline (5 milestones)
- 1999-12-30Referred To Dept Of Justice
- 2000-10-20Enforcement Action Data Entered
- 2000-12-29Complaint Filed With Court
- 2000-12-29Final Order Lodged
- 2005-02-15Final Order Entered
Case metadata
- EPA activity ID
- 51698
- Case number
- 08-2000-0301
- Lead agency
- EPA
- HQ division
- WAT
- EPA region
- 08
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- Violation of Existing AO
Sourced verbatim from EPA ECHO Enforcement Case Report for case 08-2000-0301 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.