08-1997-0144Administrative - FormalFinal Order IssuedFY 1997· Region 08

EPA v. SMITH PAVING & CONTRACTING ENTERPRISES, INC.

Case summary

RESPONDENT FAILED TO COMPLY WITH THE NOTIFICATION PROVISIONS WHICH REQUIRE THAT A FACILITY OWNER NOTIFY THE ADMINISTRATOR OF THE EPA OF ANY PHYSICAL CHANGE IN THE FACILITYWHICH MAY INCREASE ITS EMISSION RATE TO THE ATMOSPHERE OF ANY AIR POLLUTANT.RESPONDENT ALSO FAILED TO COMPLY WITH THE TEST- ING AND REPORTING PROVISIONS AND FAILED TO COMPLY WITH THE RECORD KEEPING PROVISIONS.

Defendants (1)

  • SMITH PAVINGNamed in complaintNamed in settlement

Facilities (1)

  • SMITH PAVING

    54668 HWY. 93, POLSON, MT, 59860

    Registry ID: 110007112640

Statutes cited

  • CAA 113BClean Air Act

Enforcement conclusions (1)

  • SMITH PAVING & CONTRACTINGentered 1997-07-02

    Primary law: CAA

Timeline (3 milestones)

  • 1997-07-02Final Order Issued
  • 1997-07-02Complaint Filed/Proposed Order
  • 1997-07-29Enforcement Action Data Entered

Case metadata

EPA activity ID
50785
Case number
08-1997-0144
Lead agency
EPA
HQ division
AIR
EPA region
08
Multimedia
No
Voluntary self-disclosure
No
Primary statute
Clean Air Act

Sourced verbatim from EPA ECHO Enforcement Case Report for case 08-1997-0144 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.