EPA v. CARROLL, HOWARD T ET AL/YTTRIUM PROCESSING PLANT SITE
Final Order With Specified Cost Recovery
Cost recovery
$30,000
Case summary
EPA ALLEGES THAT IS HAS A CLAIM AGAINST THE RESPONDENTS FOR RECOVERY OF PAST RESPONSE COSTS PERTAINING TO THE YTTRIUM PROCESSING PLANT SITE, LOCATED IN LARAMIE, WYOMING. WITHIN 30 DAYS AFTER THE EFFECTIVE DATE OF THIS AGREEMENT, RESPONDENTS SHALL TOGETHER PAY PAST RESPONSE COSTS IN THE AMOUNT OF $30,000.
Defendants (5)
- RIVERSIDE ACRES LIMITED PARTNERSHIPNamed in complaintNamed in settlement
- CARROLL, HOWARD TNamed in complaintNamed in settlement
- KRUEGER, ALIENE WNamed in complaintNamed in settlement
- MILLETT, CATHERINE ENamed in complaintNamed in settlement
- MILLETT, GEORGE WNamed in complaintNamed in settlement
Facilities (1)
WAUCONDA SAND & GRAVEL
BONNER & GARLAND RD, WAUCONDA, IL, 60084
Registry ID: 110009327022
Statutes cited
- CERCLA 122H — Administrative Cost Recovery Settlement
Enforcement conclusions (1)
CARROLL, HOWARD T ET AL/YTTRIUM PROCESSING PLANT Sentered 1994-03-17
Primary law: CERCLA
Timeline (4 milestones)
- 1993-05-12Complaint Filed/Proposed Order
- 1993-07-19Enforcement Action Data Entered
- 1994-03-17Final Order Issued
- 1994-03-17Enforcement Action Closed
Case metadata
- EPA activity ID
- 49709
- Case number
- 08-1993-0268
- Lead agency
- EPA
- HQ division
- CER
- EPA region
- 08
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- Administrative Cost Recovery Settlement
Sourced verbatim from EPA ECHO Enforcement Case Report for case 08-1993-0268 . Bulk data: ICIS-FEC download summary.