Skip to main content
08-1990-0050Administrative - FormalClosedFY 1990· Region 08

EPA v. HUNTER ENVIRONMENTAL SCIENCE & ENGINEERING INC

Final Order With Penalty

Penalty assessed

$2,500

Case summary

FAILURE TO SAMPLE OR ASSUME TO BE ASBESTOS MATERIAL THE EXPANSION JOINTS IN THE HEATING DUCT AT RED SANDSTONE ELEMENTARY SCHOOL. FAILURE TO PROPERLY INSPECT FOR ALL LOCATIONS OF FRIABLE AND NONFRIABLE ACBM AT RED SANDSTONE ELEMENTARY SCHOOL.

Defendants (1)

  • HUNTER ENVIRONMENTAL SCIENCE & ENGINEERNamed in complaintNamed in settlement

Facilities (1)

  • WAUCONDA SAND & GRAVEL

    BONNER & GARLAND RD, WAUCONDA, IL, 60084

    Registry ID: 110009327022

Statutes cited

  • TSCA 15Prohibited Acts

Enforcement conclusions (1)

  • HUNTER ENVIRONMENTAL SCIENCE & ENGINEERING INCentered 1990-12-17

    Primary law: TSCA

    Federal penalty: $2,500

Timeline (5 milestones)

  • 1990-03-29Enforcement Action Data Entered
  • 1990-03-29Complaint Filed/Proposed Order
  • 1990-12-17Final Order Issued
  • 1991-03-13Compliance Achieved
  • 1991-03-13Enforcement Action Closed

Case metadata

EPA activity ID
48585
Case number
08-1990-0050
Lead agency
EPA
HQ division
TOX
EPA region
08
Multimedia
No
Voluntary self-disclosure
No
Primary statute
Prohibited Acts

Sourced verbatim from EPA ECHO Enforcement Case Report for case 08-1990-0050 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.