EPA v. HURON, CITY OF
Case summary
FAILURE TO COMPLY WITH COMPLIANCE SCHEDULE FOR CONSTRUCTION OF NEW OR UPGRADED FACILITIES BY 1 NOV 1985. FAILURE TO BEGIN CONSTRUCTION OF IMPROVEMENTS TO ITS SEQUENCING BATCH REACTOR FACILITIES BY 1 APR 1989 UNDER AO 88-22-C, AUG 23, 1988. FAILURE TO BEGIN CONSTRUCTION OF NEW OR UPGRADED FACILITIES TO MEET ITS PERMIT FINAL EFFLUENT LIMITS NO LATER THAN JUL 1, 1989.
Defendants (1)
- HURON, CITY OFNamed in complaint
Facilities (1)
WAUCONDA SAND & GRAVEL
BONNER & GARLAND RD, WAUCONDA, IL, 60084
Registry ID: 110009327022
Statutes cited
- CWA 309 — Violation of Existing AO
Timeline (2 milestones)
- 1990-01-02Enforcement Action Data Entered
- 1990-01-02Complaint Filed/Proposed Order
Case metadata
- EPA activity ID
- 48567
- Case number
- 08-1990-0032
- Lead agency
- EPA
- HQ division
- WAT
- EPA region
- 08
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- Violation of Existing AO
Sourced verbatim from EPA ECHO Enforcement Case Report for case 08-1990-0032 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.