07-2025-1001JudicialFinal Order EnteredFY 2025· Region 07
EPA v. Iowa-Nebraska Light & Power Company Site CERCLA 107A 106A
Final Order No Penalty
Case summary
Consent decree for remedial design and remedial action. Payment of oversight costs. In exchange for the settlement, PRPs will receive a covenant not to sue for Operable Unit 1.
Defendants (3)
- Nebraska Public Power DistrictNamed in complaintNamed in settlement
- Brightspeed Kansas Holdings, LLC,Named in complaintNamed in settlement
- Black Hills Nebraska Gas, LLC,Named in complaintNamed in settlement
Facilities (1)
IOWA-NEBRASKA LIGHT & POWER CO
102-104 SOUTH 7TH STREET, NORFOLK, NE, 68701
Registry ID: 110009298508
Statutes cited
- CERCLA 106A — Imminent & Substantial Endangerment Order
- CERCLA 107A — Cost Recovery
Enforcement conclusions (1)
Iowa-Nebraska Light & Power Company Site CERCLA 107A 106Aentered 2025-01-27
Primary law: CERCLA
Timeline (5 milestones)
- 2024-10-30Referred To Dept Of Justice
- 2024-11-01Final Order Lodged
- 2024-11-01Complaint Filed With Court
- 2025-01-27Final Order Entered
- 2025-01-31Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3604247429
- Case number
- 07-2025-1001
- Lead agency
- EPA
- EPA region
- 07
- Voluntary self-disclosure
- No
- Primary statute
- Imminent & Substantial Endangerment Order
Sourced verbatim from EPA ECHO Enforcement Case Report for case 07-2025-1001 . Bulk data: ICIS-FEC download summary.