EPA v. Joseph Coffman CWA 309A AO For Compliance
Final Order No Penalty
Case summary
Between November 2023 and January 2024, Respondent, using earth moving equipment, placed concrete blocks, moved gravel, and installed in-stream fencing in an effort the halt cutbank erosion on his property, impacting the bottom elevation of the Creek. This work was performed without first obtaining an CWA 404 permit. Approximately 957 feet of Saline Creek were impacted.
Defendants (1)
- Joseph CoffmanNamed in complaintNamed in settlement
Facilities (1)
JOSEPH COFFMAN
ROUTE N NEAR MINNITH RD, MINNITH, MO, 63673
Registry ID: 110071721842
Statutes cited
- CWA 404 — Permits for Dredge and Fill Material
Enforcement conclusions (1)
Joseph Coffman CWA 309A AO For Complianceentered 2026-03-04
Primary law: CWA
Timeline (3 milestones)
- 2026-03-04Final Order Issued
- 2026-03-04Complaint Filed/Proposed Order
- 2026-04-22Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3604884991
- Case number
- 07-2025-0107
- Lead agency
- EPA
- EPA region
- 07
- Voluntary self-disclosure
- No
- Primary statute
- Permits for Dredge and Fill Material