EPA v. Ely?s, Inc. CAA 113A Admin Compliance Order (Non-Penalty)
Final Order No Penalty
Case summary
On September 26, 2023, the EPA conducted an inspection at Respondent?s facility, which is subject to the 40 CFR Part 68 Program 2 prevention requirements. Respondent was found in violation of these requirements, and also failed to ensure and document that the process is designed in compliance with recognized and generally accepted good engineering practices for anhydrous ammonia retailers. The order requires compliance with these requirements.
Defendants (1)
- Ely�s, Inc.Named in complaintNamed in settlement
Facilities (1)
ELY'S INC
101 UNIVERSITY STREET, GUIDE ROCK, NE, 68942-8082
Registry ID: 110000559967
Statutes cited
- CAA 112[R][7] — Prevention of Accidental Release/Risk Management Plans (RMPs)
Enforcement conclusions (1)
Ely?s, Inc. CAA 113A Admin Compliance Order (Non-Penalty)entered 2025-08-20
Primary law: CAA
Timeline (3 milestones)
- 2025-08-20Complaint Filed/Proposed Order
- 2025-08-20Final Order Issued
- 2025-08-21Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3604499437
- Case number
- 07-2024-0145
- Lead agency
- EPA
- EPA region
- 07
- Voluntary self-disclosure
- No
- Primary statute
- Prevention of Accidental Release/Risk Management Plans (RMPs)