07-2020-0126Administrative - FormalClosedFY 2020· Region 07

EPA v. WELEK CONSTRUCTION COMPANY

Final Order With Penalty

Case summary

Failure or refusal to permit entry or inspection; Failure to obtain initial firm certification from EPA; Failure of a firm to assign a certified renovator; and Failure to post signs clearly defining the work area and warning occupants and other persons not involved in renovation activities to remain outside of the work area; to prepare, to the extent practicable, signs in the primary language of the occupants; and/or to post signs before beginning the renovation and makes sure they remain in place and readable until post-renovation cleaning verification have been completed.

Defendants (1)

  • WELEK CONSTRUCTION COMPANYNamed in complaintNamed in settlement

Facilities (1)

  • WELEK CONSTRUCTION COMPANY

    603 EDGEWOOD DRIVE, COLUMBIA, MO, 65203

    Registry ID: 110070672045

Statutes cited

  • TSCA 409Lead: Violation of Section 1018

Enforcement conclusions (1)

  • WELEK CONSTRUCTION COMPANYentered 2020-05-11

    Primary law: TSCA

    Federal penalty: $10,801

Timeline (6 milestones)

  • 2020-05-11Final Order Issued
  • 2020-05-11Complaint Filed/Proposed Order
  • 2020-05-13Enforcement Action Data Entered
  • 2020-05-27Pipeline Closed
  • 2020-05-27Compliance Achieved
  • 2020-05-27Enforcement Action Closed

Case metadata

EPA activity ID
3602194491
Case number
07-2020-0126
Lead agency
EPA
EPA region
07
Voluntary self-disclosure
No
Primary statute
Lead: Violation of Section 1018