07-2019-0206Administrative - FormalClosedFY 2019· Region 07

EPA v. JSK ELECTRICAL & CONSTRUCTION LLC

Final Order With Penalty

Case summary

RESPONDENT FAILED TO COMPLY WITH RRP REQUIREMENTS INCLUDING THE REQUIREMENT TO OBTAIN INITIAL FIRM CERTIFICATION; TO ASSIGN A CERTIFIED RENOVATOR; POST SIGNS DEFINING THE WORK AREA AND WARN OCCUPANTS AND OTHER PERSONS TO REMAIN OUTSIDE THE WORK AREA; TO CLOSE DOORS AND WINDOWS IN THE AREA, AND TO COVER THE FLOOR WITH IMPERMEABLE MATERIAL.

Defendants (1)

  • JSK ELECTRICAL & CONSTRUCTION LLCNamed in complaintNamed in settlement

Facilities (1)

  • PATRIOT RESTORATION, LLC

    113 E HALE STREET, SPRING HILL, KS, 66083

    Registry ID: 110070239079

Statutes cited

  • TSCA 402ALead: Abatement
  • TSCA 409Lead: Violation of Section 1018

Enforcement conclusions (1)

  • JSK ELECTRICAL & CONSTRUCTION LLCentered 2019-07-09

    Primary law: TSCA

    Federal penalty: $794

Timeline (6 milestones)

  • 2019-07-09Complaint Filed/Proposed Order
  • 2019-07-09Final Order Issued
  • 2019-07-12Enforcement Action Data Entered
  • 2019-08-07Enforcement Action Closed
  • 2019-08-07Compliance Achieved
  • 2019-08-07Pipeline Closed

Case metadata

EPA activity ID
3601902467
Case number
07-2019-0206
Lead agency
EPA
EPA region
07
Voluntary self-disclosure
No
Primary statute
Lead: Abatement