EPA v. 2ND AND SMELTER (FORMER ROBERT LANYON SMELTER)
Final Order No Penalty
Case summary
THIS IS AN ADMINISTRATIVE SETTLEMENT AGREEMENT AND ORDER ON CONSENT BETWEEN EPA AND SOUTH KANSAS AND OKLAHOMA RAILROAD, LLC AND WATCO COMPANIES LLC FOR CLEANUP OF LEAD CONTAMINATED SOIL RESULTING FROM HISTORIC OPERATIONS OF A ZINC SMELTER
Defendants (2)
- WATCO COMPANIES LLCNamed in complaintNamed in settlement
- KANSAS AND OKLAHOMA RAILROADNamed in complaintNamed in settlement
Facilities (1)
2ND AND SMELTER
2ND AND SMELTER, PITTSBURG, KS, 66762
Registry ID: 110067352705
Statutes cited
- CERCLA 104E2 — Information and/or Access
- CERCLA 122A — Agreement to Perform Work Under 104B
- CERCLA 106A — Imminent & Substantial Endangerment Order
Enforcement conclusions (1)
2ND AND SMELTER (FORMER ROBERT LANYON SMELTER)entered 2017-08-29
Primary law: CERCLA
Timeline (2 milestones)
- 2017-08-29Final Order Issued
- 2017-09-27Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3601189854
- Case number
- 07-2017-0467
- Lead agency
- EPA
- EPA region
- 07
- Voluntary self-disclosure
- No
- Primary statute
- Information and/or Access
Sourced verbatim from EPA ECHO Enforcement Case Report for case 07-2017-0467 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.