EPA v. WEST LAKE LANDFILL
Final Order No Penalty
Case summary
ADMINISTRATIVE SETTLEMENT AGREEMENT AND ORDER ON CONSENT FOR REMOVAL ACTION - PRECONSTRUCTION WORK.L PREPARATORY WORK FOR CONSTRUCTION OF AN ISOLATION BARRIER AT THE SITE. THE ISOLATION BARRIER WORK WILL BE EMBODIED IN A SUBSEQUENT AGREEMENT.
Defendants (1)
- WEST LAKE LANDFILLNamed in complaintNamed in settlement
Facilities (1)
BRIDGETON LANDFILL, LLC
13570 ST.CHARLES ROCK RD, BRIDGETON, MO, 63044
Registry ID: 110071102406
Statutes cited
- CERCLA 122H — Administrative Cost Recovery Settlement
- CERCLA 107A — Cost Recovery
- CERCLA 104E3 — Entry Access
Enforcement conclusions (1)
WEST LAKE LANDFILLentered 2014-04-16
Primary law: CERCLA
Timeline (3 milestones)
- 2014-04-16Complaint Filed/Proposed Order
- 2014-04-16Final Order Issued
- 2014-06-19Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3400251966
- Case number
- 07-2014-0175
- Lead agency
- EPA
- EPA region
- 07
- Voluntary self-disclosure
- No
- Primary statute
- Administrative Cost Recovery Settlement