EPA v. PALO ALTO COUNTY BOARD OF SUPERVISORS
Final Order No Penalty
Case summary
DRAINAGE DISTRICT, CONSULTANT AND CONTRACTOR BEGAN WORK IN JURISDICTIONAL WATERS PRIOR TO ISSUANCE OF REQUIRED CWA 404 PERMIT BY THE ARJMY CORPS OF ENGINEERS. THIS ADMINISTRATIVE ORDER REQUIRES COMPLETION OF THE WORK AND MITIGATION IN ACCORDANCE WITH APPROVED WORK PLAN.
Defendants (3)
- C J MOYNA & SONS, INCNamed in complaintNamed in settlement
- I & S GROUP, INCNamed in complaintNamed in settlement
- PALO ALTO COUNTY BOARD OF SUPERVISORSNamed in complaintNamed in settlement
Facilities (1)
PALO ALTO COUNTY BOARD OF SUPERVISORS
43.25508 -94.609108, EMMETSBURG, IA, 50536
Registry ID: 110055490507
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
- CWA 404 — Permits for Dredge and Fill Material
Enforcement conclusions (1)
PALO ALTO COUNTY BOARD OF SUPERVISORSentered 2013-06-14
Primary law: CWA
Timeline (6 milestones)
- 2013-06-14Final Order Issued
- 2013-06-14Complaint Filed/Proposed Order
- 2013-07-23Enforcement Action Data Entered
- 2019-03-07Enforcement Action Closed
- 2019-03-07Compliance Achieved
- 2019-03-07Pipeline Closed
Case metadata
- EPA activity ID
- 3400136878
- Case number
- 07-2013-0111
- Lead agency
- EPA
- EPA region
- 07
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit