07-2012-0223Administrative - FormalClosedFY 2012· Region 07
EPA v. BIG RIVER MINE TAILINGS SUPERFUND SITE
Final Order With Specified Cost Recovery
Case summary
ADMINISTRATIVE ORDER REQUIRING SETTLING PARTY TO PAY EPA $42,077.71 IN RESPONSE COSTS.
Defendants (1)
- THE DOE RUN RESOURCES CORPORATIONNamed in complaintNamed in settlement
Facilities (1)
BIG RIVER MINE TAILINGS/ST. JOE MINERALS CORP.
SECTION 25 26 35 & 36 T37N R4E, DESLOGE, MO, 63601
Registry ID: 110009351860
Statutes cited
- CERCLA 122H — Administrative Cost Recovery Settlement
Enforcement conclusions (1)
BIG RIVER MINE TAILINGS SUPERFUND SITEentered 2012-08-30
Primary law: CERCLA
Timeline (5 milestones)
- 2012-08-30Final Order Issued
- 2012-08-30Complaint Filed/Proposed Order
- 2012-09-17Enforcement Action Data Entered
- 2012-09-30Enforcement Action Closed
- 2012-09-30Pipeline Closed
Case metadata
- EPA activity ID
- 3000059276
- Case number
- 07-2012-0223
- Lead agency
- EPA
- EPA region
- 07
- Voluntary self-disclosure
- No
- Primary statute
- Administrative Cost Recovery Settlement
Sourced verbatim from EPA ECHO Enforcement Case Report for case 07-2012-0223 . Bulk data: ICIS-FEC download summary.