Skip to main content
07-2004-0018JudicialClosedFY 2004· Region 07

EPA v. DURACELL, INC

Final Order With Specified Cost Recovery

Case summary

IN 2000, EPA PERFORMED A FUND-LEAD TIME-CRITICAL REMOVAL OF BATTERY WASTE AND LEAD-CONTAMINATED SOIL. COST OF THE REMOVAL WAS APPROXIMATELY $1,000,000. WITNESS STATEMENTS LEAD TO THE CONCLUSION THAT THE BATTERIES WERE FROM A FORMER BATTERY FACTORY LOCATED IN DUBUQUE, IOWA, APPROXIMATELY 1.5 MILES FROM THE SITE. THE BATTERY FACTORY WAS OPERATED FROM 1936-1957 BY GENERAL DRY BATTERIES, INC. THE CORPORATION WAS PURCHASED BY A CORPORATE PREDECESSOR OR OF DURACELL, INC IN 1956 AND SUBSEQUENTLY SHUT DOWN IN 1957. THE BATTERIES RECEIVED FROM GENERAL DRY BATTERIES WERE CRACKED AND PROCESSED BY AN INDIVIDUAL AT THE SITE TO RECLAIM THE ZINC. THE ZINC WAS SOLD AND INCORPORATED INTO A GALVANIZING PROCESS.

Defendants (1)

  • DURACELL, INCNamed in complaintNamed in settlement

Facilities (1)

  • DURACELL, INC

    11399 ROUTE 52 NORTH, SAGEVILLE, IA, 52001

    Registry ID: 110009325042

Statutes cited

  • CERCLA 107ACost Recovery

Enforcement conclusions (1)

  • DURACELL, INCentered 2006-08-17

    Primary law: CERCLA

Timeline (6 milestones)

  • 2003-11-07Referred To Dept Of Justice
  • 2003-11-12Enforcement Action Data Entered
  • 2006-06-08Final Order Lodged
  • 2006-06-08Complaint Filed With Court
  • 2006-08-17Final Order Entered
  • 2007-10-18Enforcement Action Closed

Case metadata

EPA activity ID
108249
Case number
07-2004-0018
DOJ docket
90-11-2-08217
Lead agency
EPA
EPA region
07
Voluntary self-disclosure
No
Primary statute
Cost Recovery

Sourced verbatim from EPA ECHO Enforcement Case Report for case 07-2004-0018 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.