EPA v. ARMOUR ROAD NPL SITE; U.S. BORAX, INC
Litigated No Penalty
Case summary
ON MARCH 6, 2003, A PRN WAS SENT TO DOJ SEEKING DOJ'S APPROVAL OF A SETTLEMENT WHICH WOULD RESULT IN THE COMPROMISE OF A CLAIM INVOLVING TOTAL RESPONSE COSTS WHICH ARE EXPECTED TO EXCEED $500,000, EXCLUDING INTEREST. DURING THE COURSE OF NEGOTIATING THIS SETTLEMENT AGREEMENT IT WAS AGREED THAT THE PARTIES WOULD SETTLE BY WAY OF A CONSENT DECREE RATHER THAN AN ADMINISTRATIVE ORDER ON CONSENT.
Defendants (5)
- U.S. BORAX, INCNamed in complaintNamed in settlement
- BURLINGTON NORTHERN SANTA FE RAILWAY COMPANYNamed in complaintNamed in settlement
- ESTATE OF CHARLES F READE, SRNamed in complaintNamed in settlement
- TERRACON, INCNamed in complaintNamed in settlement
- HARDEE'S FOOD SYSTEMS, INCNamed in complaintNamed in settlement
Facilities (1)
BORAX, INC
2251 ARMOUR ROAD, NORTH KANSAS CITY, MO, 64116
Registry ID: 110018918947
Statutes cited
- CERCLA 106A — Imminent & Substantial Endangerment Order
Enforcement conclusions (1)
ARMOUR ROAD NPL SITE; U.S. BORAX, INCentered 2004-06-03
Primary law: CERCLA
Timeline (8 milestones)
- 2003-03-06PRN Sent
- 2003-07-03Enforcement Action Data Entered
- 2004-03-17Referred To Dept Of Justice
- 2004-04-09Final Order Lodged
- 2004-04-09Complaint Filed With Court
- 2004-06-03Final Order Entered
- 2006-05-06Enforcement Action Closed
- 2006-05-06Pipeline Closed
Case metadata
- EPA activity ID
- 98592
- Case number
- 07-2003-0184
- Lead agency
- EPA
- EPA region
- 07
- Voluntary self-disclosure
- No
- Primary statute
- Imminent & Substantial Endangerment Order
Sourced verbatim from EPA ECHO Enforcement Case Report for case 07-2003-0184 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.