07-1999-0036Administrative - FormalClosedFY 1999· Region 07
EPA v. POOLS PRAIRIE SITE, LONG-TERM WATER SUPPLY ORDER, NEOSHO, MO
Final Order With Specified Cost Recovery
Cost recovery
$60,000
Compliance action
$1,700,000
Case summary
1/4/99: CERCLA NON-TIME CRITICAL REMOVAL ACTION WITH RECOVE RY OF EPA OVERSIGHT COSTS.
Defendants (4)
- BOEING NORTH AMERICAN, INC.Named in complaintNamed in settlement
- MISSOURI ARMY NATIONAL GUARDNamed in complaintNamed in settlement
- TELEDYNE INDUSTRIES, INC.Named in complaintNamed in settlement
- U.S. DEPARTMENT OF DEFENSENamed in complaintNamed in settlement
Facilities (1)
900 BUILDING
6000 HOWARD BUSH DRIVE, NEOSHO, MO, 64850
Registry ID: 110009338421
Statutes cited
- CERCLA 106 — Imminent & Substantial Endangerment Order
Enforcement conclusions (1)
POOLS PRAIRIE SITE, NEOSHO, MOentered 1998-12-30
Primary law: CERCLA
Timeline (5 milestones)
- 1998-12-30Complaint Filed/Proposed Order
- 1998-12-30Final Order Issued
- 1999-01-04Enforcement Action Data Entered
- 2008-09-30Enforcement Action Closed
- 2008-09-30Compliance Achieved
Case metadata
- EPA activity ID
- 46233
- Case number
- 07-1999-0036
- Lead agency
- EPA
- HQ division
- CER
- Branch
- SPFD
- EPA region
- 07
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- Imminent & Substantial Endangerment Order
Sourced verbatim from EPA ECHO Enforcement Case Report for case 07-1999-0036 . Bulk data: ICIS-FEC download summary.