06-2026-3575Administrative - FormalFinal Order IssuedFY 2026· Region 06

EPA v. Village of Parks WTP-Parks, LA-RMP AOC-FY 2026

Case summary

On April 7, 2014, EPA RMP Reporting Center sent a letter to Respondent, notifying Respondent of its failure to update the RMP on file with EPA for the Facility. EPA conducted an investigation of the Facility on July 14, 2026, to determine Respondent?s compliance with Section 112(r) of the CAA, 42 U.S.C. ? 7412(r), and 40 C.F.R. Part 68 (the ?Investigation?). Based upon the information gathered during the Investigation, EPA determined that the Respondent violated certain provisions of the CAA.

Defendants (1)

  • Village of Parks WTPNamed in complaintNamed in settlement

Facilities (1)

  • THE VILLAGE OF PARKS WATER TREATMENT PLANT

    1010 MARTIN STREET, PARKS, LA, 70582

    Registry ID: 110040058898

Statutes cited

  • CAA 112[R][7]Prevention of Accidental Release/Risk Management Plans (RMPs)

Enforcement conclusions (1)

  • Village of Parks WTP-Parks, LA-RMP AOC-FY 2026entered 2026-08-10

    Primary law: CAA

Timeline (2 milestones)

  • 2026-08-10Final Order Issued
  • 2026-08-13Enforcement Action Data Entered

Case metadata

EPA activity ID
3605049999
Case number
06-2026-3575
Lead agency
EPA
Branch
ECDSC
EPA region
06
Voluntary self-disclosure
No
Primary statute
Prevention of Accidental Release/Risk Management Plans (RMPs)