EPA v. Blue Tide Baytown, LLC-Baytown, TX-RMP AOC-FY 2026
Case summary
On January 29, 2025, there was an accidental release (the Incident ) of hydrogen from a nitrogen hose line at the facility. On August 18, 2025, EPA sent Respondent a Notice letter. On September 5, 2025, and on various other occasions, EPA conferred with Respondent regarding the violations alleged herein and provided an opportunity for Respondent to submit additional information or materials. Based upon the information gathered during the Investigation, EPA determined that Respondent violated certain provisions of the CAA. EPA and Respondent entered into a Consent Agreement and Final Order, Docket No. CAA-06-2026-3521 to resolve Respondent's liability for federal civil penalties for the alleged violation in this Order.
Defendants (1)
- Blue Tide Baytown, LLCNamed in complaintNamed in settlement
Facilities (1)
TOPSAIL ENERGY BAYTOWN
6651 W BAY RD, BAYTOWN, TX, 77523-8615
Registry ID: 110070032056
Statutes cited
- CAA 112[R][7] — Prevention of Accidental Release/Risk Management Plans (RMPs)
Enforcement conclusions (1)
Blue Tide Baytown, LLC-Baytown, TX-RMP AOC-FY 2026entered 2026-02-03
Primary law: CAA
Timeline (3 milestones)
- 2026-02-02Complaint Filed/Proposed Order
- 2026-02-03Final Order Issued
- 2026-02-10Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3604717733
- Case number
- 06-2026-3521
- Lead agency
- EPA
- Branch
- ECDSC
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- Prevention of Accidental Release/Risk Management Plans (RMPs)
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2026-3521 . Bulk data: ICIS-FEC download summary.