06-2025-3416Administrative - FormalClosedFY 2025· Region 06

EPA v. Battle Ridge Processing Plant-Cushing, OK-RMP AOC-FY 2025

Final Order No Penalty

Case summary

On April 6, 2023 EPA RMP Reporting Center sent a letter to Respondent, notifying Respondent of its failure to update the RMP on file with EPA for the Facility. EPA conducted an investigation of the Facility on April 24, 2025, to determine Respondent's compliance with Section 112(r) of the CAA, 42 U.S.C. ? 7412(r), and 40 C.F.R. Part 68 (the Investigation ).Based upon the information gathered during the Investigation, EPA determined that the Respondent violated certain provisions of the CAA.

Defendants (1)

  • Battle Ridge Processing PlantNamed in complaintNamed in settlement

Facilities (1)

  • TOM STACK LLC / BATTLE RIDGE PLANT

    0.1 MI W OF N3480/E0740 RD, CUSHING, OK, 74023

    Registry ID: 110063223818

Statutes cited

  • CAA 112[R][7]Prevention of Accidental Release/Risk Management Plans (RMPs)

Enforcement conclusions (1)

  • Battle Ridge Processing Plant-Cushing, OK-RMP AOC-FY 2025entered 2025-06-03

    Primary law: CAA

Timeline (5 milestones)

  • 2025-06-03Final Order Issued
  • 2025-06-03Complaint Filed/Proposed Order
  • 2025-06-09Enforcement Action Data Entered
  • 2025-06-30Air Resolved
  • 2025-06-30Enforcement Action Closed

Case metadata

EPA activity ID
3604426093
Case number
06-2025-3416
Lead agency
EPA
Branch
ECDSC
EPA region
06
Voluntary self-disclosure
No
Primary statute
Prevention of Accidental Release/Risk Management Plans (RMPs)