EPA v. WR GRACE-SUPER HIGH ACTIVITY CATALYST PLANT-Norco, LA-RMP CAFO w SEP-FY 2025
Final Order With Penalty
Case summary
EPA conducted an inspection of the Facility on May 3-5, 2022, to determine Respondent's compliance with Section112(r) of the CAA, 42 U.S.C. ? 7412(r), and 40 C.F.R. Part 68. On June 04, 2024, EPA sent Respondent a Notice letter. On August 28, 2024, EPA responded to the documentation and information received from Respondent as a result of the opportunity to confer and articulated EPA's position concerning Respondent's compliance with Section 112(r) of the CAA, 42 U.S.C. ? 7412(r). Based upon the information gathered 1uring the Inspection, EPA determined that Respondent violated certain provisions of the CAA.
Defendants (1)
- W.R. Grace SHAC PlantNamed in complaintNamed in settlement
Facilities (1)
W R GRACE & CO - CONN - SUPER HIGH ACTIVITY CATALYST PLANT
16122 RIVER RD, NORCO, LA, 70079
Registry ID: 110071722803
Statutes cited
- CAA 112[R][7] — Prevention of Accidental Release/Risk Management Plans (RMPs)
Enforcement conclusions (1)
WR GRACE-SUPER HIGH ACTIVITY CATALYST PLANT-Norco, LA-RMP CAFO w SEP-FY 2025entered 2025-07-25
Primary law: CAA
Federal penalty: $20,873 · SEP: $50,097
Timeline (2 milestones)
- 2025-07-25Final Order Issued
- 2025-07-29Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3604470530
- Case number
- 06-2025-3343
- Lead agency
- EPA
- Branch
- ECDSC
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- Prevention of Accidental Release/Risk Management Plans (RMPs)
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2025-3343 . Bulk data: ICIS-FEC download summary.