06-2025-3309Administrative - FormalClosedFY 2025· Region 06

EPA v. Natgasoline LLC-Beaumont, TX-RMP ESA-FY 2025

Final Order With Penalty

Case summary

On February 5, 2024, EPA Risk Management Program Reporting Center sent a letter to Respondent, notifying Respondent of its failure to update the Risk Management Plan on file with the EPA for its facility located in Beaumont, Texas. Facilities subject to the Risk Management Program (RMP) regulations at 40 C.F.R. Part 68 are required to submit an updated Risk Management Plan at least once every five years. The EPA's review indicates that the update for the facility was not submitted by the required due date of January 7, 2024.

Defendants (1)

  • Natgasoline LLCNamed in complaintNamed in settlement

Facilities (1)

  • NATGASOLINE LLC

    2366 SULPHUR PLANT ROAD, BEAUMONT, TX, 77705

    Registry ID: 110070507083

Statutes cited

  • CAA 112[R][7]Prevention of Accidental Release/Risk Management Plans (RMPs)

Enforcement conclusions (1)

  • Natgasoline LLC-Beaumont, TX-RMP ESA-FY 2025entered 2025-01-14

    Primary law: CAA

    Federal penalty: $2,000

Timeline (5 milestones)

  • 2024-12-17Complaint Filed/Proposed Order
  • 2025-01-14Final Order Issued
  • 2025-01-14Compliance Achieved
  • 2025-01-16Enforcement Action Data Entered
  • 2025-01-16Enforcement Action Closed

Case metadata

EPA activity ID
3604230510
Case number
06-2025-3309
Lead agency
EPA
Branch
ECDSC
EPA region
06
Voluntary self-disclosure
No
Primary statute
Prevention of Accidental Release/Risk Management Plans (RMPs)

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2025-3309 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.