EPA v. 2020 Harris Partners, LLC (OS2326) MIT Failure
Case summary
On August 5, 2025, EPA Region 6 issued a Final Administrative Order (Final Order) under its authority pursuant to under its authority pursuant to Section 1423(c) of the Safe Drinking Water Act to 2020 Harris Partners, LLC. (Respondent) located in Barnsdall, Oklahoma. The Final Order was issued in response to violations of 40 C.F.R. Sections 147.2903(b), 147.2909, 147.2912(a) by failing to successfully demonstrate mechanical integrity of their injection well. The Final Order requires Respondent to successfully demonstrate mechanical integrity of the injection well, plug the injection well or convert it to production use. Respondent must respond to EPA Region 6 within 30 days.
Defendants (1)
- 2020 Harris Partners, LLCNamed in complaintNamed in settlement
Facilities (1)
OS2326 - WELL NO. W-11 (E)
NE/4, SEC. 16, T 25N, R 12E, OCHELATA, OK, 74051
Registry ID: 110014427067
Statutes cited
- SDWA 1422/1423 — UIC Regulations Classes I - V
- SDWA 1421 — UIC Regulations
Enforcement conclusions (1)
2020 Harris Partners, LLC (OS2326) MIT Failureentered 2025-08-05
Primary law: SDWA
Timeline (3 milestones)
- 2025-05-14Complaint Filed/Proposed Order
- 2025-08-05Final Order Issued
- 2025-08-07Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3604482680
- Case number
- 06-2025-1111
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- UIC Regulations Classes I - V
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2025-1111 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.