06-2024-2714Administrative - FormalClosedFY 2024· Region 06

EPA v. Future Frontiers, LLC

Final Order No Penalty

Case summary

Short section of stream was filled as part of development. Mitigation to offset impact will be performed in the same watershed, just upstream, with public access to enhanced aquatic resources.

Defendants (1)

  • Future Frontiers, LLCNamed in complaintNamed in settlement

Facilities (1)

  • FUTURE FRONTIERS LLC

    3111 NEALY WAY, LONGVIEW, TX, 75605

    Registry ID: 110071399235

Statutes cited

  • CWA 404Permits for Dredge and Fill Material

Enforcement conclusions (1)

  • Future Frontiers, LLCentered 2024-05-02

    Primary law: CWA

Timeline (3 milestones)

  • 2024-05-02Enforcement Action Data Entered
  • 2024-05-02Final Order Issued
  • 2024-12-02Enforcement Action Closed

Case metadata

EPA activity ID
3603969027
Case number
06-2024-2714
Lead agency
EPA
Branch
WTREB
EPA region
06
Voluntary self-disclosure
No
Primary statute
Permits for Dredge and Fill Material

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2024-2714 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.