06-2024-1733Administrative - FormalFinal Order IssuedFY 2024· Region 06

EPA v. Lake Hubbard Steam Electric Station (Luminent Generation Company) (TX0001023)

Case summary

The Lake Hubbard Steam Electric Station was issued an Administrative Order on March 25, 2023. The facility will have thirty (30) days to respond on how they will return to compliance. An EJ screening was performed and was determined to not fall within the 90th percentile range.

Defendants (1)

  • Luminant Generation Company LLCNamed in settlement

Facilities (1)

  • LAKE HUBBARD SES

    555 BARNES BRIDGE RD, SUNNYVALE, TX, 75182

    Registry ID: 110035782891

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • Lake Hubbard Steam Electric Station (TX0001023)entered 2024-03-25

    Primary law: CWA

Timeline (2 milestones)

  • 2024-03-25Final Order Issued
  • 2024-03-26Enforcement Action Data Entered

Case metadata

EPA activity ID
3603933070
Case number
06-2024-1733
Lead agency
EPA
Branch
ECDWM
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2024-1733 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.