Expedited Settlement Agreement sent to High Mark Energy Operating, LLC on August 17, 2023 for deficiencies found at there facility during an inspection on June 6, 2023. Final Order issued on September 18, 2023.
Defendants (2)
- High Mark Energy Operating, LLCNamed in complaintNamed in settlement
- Aaron TanquaryNamed in complaintNamed in settlement
Facilities (1)
LENA SMITH-LEWIS BUSBY-PATTERSON B5 - TANK BATTERY
OFF COUNTY ROAD 3665, ALLEN, OK, 74828
Statutes cited
- CWA 311J — SPCC and/or Federal Response Plan Violations
Enforcement conclusions (1)
High Mark Energy Operating, LLC - Lena Smith - Lewis Busby - Patterson B5 Facility - ESAentered 2023-09-18
Primary law: CWA
Federal penalty: $781
Timeline (3 milestones)
- 2023-08-17Complaint Filed/Proposed Order
- 2023-08-24Enforcement Action Data Entered
- 2023-09-18Final Order Issued
Case metadata
- EPA activity ID
- 3603694140
- Case number
- 06-2023-4321
- Lead agency
- EPA
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- SPCC and/or Federal Response Plan Violations