06-2023-4316Administrative - FormalClosedFY 2023· Region 06
EPA v. R. Baker Oil, LLC - Brunner No. 1 Tank Battery
Final Order With Penalty
Case summary
Penalty Action for failure to comply with 40 CFR 112
Defendants (2)
- R. Baker Oil, LLCNamed in complaintNamed in settlement
- Mr. Ricky BakerNamed in complaintNamed in settlement
Facilities (1)
BRUNNER NO. 1 TANK BATTERY
OF US HIGHWAY 270, HOLDENVILLE, OK, 74848
Statutes cited
- CWA 311J — SPCC and/or Federal Response Plan Violations
Enforcement conclusions (1)
R. Baker Oil, LLC - Brunner No. 1 Tank Batteryentered 2023-09-20
Primary law: CWA
Federal penalty: $625
Timeline (4 milestones)
- 2023-07-24Complaint Filed/Proposed Order
- 2023-07-31Enforcement Action Data Entered
- 2023-09-20Final Order Issued
- 2023-09-21Enforcement Action Closed
Case metadata
- EPA activity ID
- 3603668461
- Case number
- 06-2023-4316
- Lead agency
- EPA
- Branch
- ECDWE
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- SPCC and/or Federal Response Plan Violations