EPA v. Prysmian Cables & Systems
Final Order With Penalty
Case summary
Data mining several EPA databases discovered the facility failed to certify reporting forms for 2023 on or before July 3, 2023, for acetophenone, copper, lead, and methanol. A proposed settlement was offered to the facility of which they accepted. A CAFO closed the case on 9/12/2023.
Defendants (1)
- Prysmian Cables & SystemsNamed in complaintNamed in settlement
Facilities (1)
GENERAL CABLE INDUSTRIES MARSHALL PLANT
HIGHWAY 80 EAST, SCOTTSVILLE, TX, 756880430
Registry ID: 110000598915
Statutes cited
- EPCRA 313 — Toxic Chemical Release Reporting (TRI)
Enforcement conclusions (1)
Prysmian Cables & Systemsentered 2023-09-12
Primary law: EPCRA
Federal penalty: $32,649
Timeline (3 milestones)
- 2023-09-12Complaint Filed/Proposed Order
- 2023-09-12Final Order Issued
- 2023-09-12Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3603711989
- Case number
- 06-2023-0573
- Lead agency
- EPA
- Branch
- ECDS
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- Toxic Chemical Release Reporting (TRI)
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2023-0573 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.