06-2022-4326Administrative - FormalClosedFY 2022· Region 06
EPA v. Moran-K Oil, LLC - BHP Central Tank Battery
Final Order With Penalty
Case summary
Penalty Action for failure to comply with 40 CFR 112
Defendants (2)
- Moran-K Oil, LLCNamed in complaintNamed in settlement
- Mr. Everett MoranNamed in complaintNamed in settlement
Facilities (1)
BHP CENTRAL TANK BATTERY
OFF COUNTY ROAD 1305, WEWOKA, OK, 74884
Statutes cited
- CWA 311J — SPCC and/or Federal Response Plan Violations
Enforcement conclusions (1)
Moran-K Oil, LLC - BHP Central Tank Batteryentered 2022-10-31
Primary law: CWA
Federal penalty: $2,219
Timeline (4 milestones)
- 2022-07-22Complaint Filed/Proposed Order
- 2022-07-25Enforcement Action Data Entered
- 2022-10-31Final Order Issued
- 2022-11-28Enforcement Action Closed
Case metadata
- EPA activity ID
- 3603293307
- Case number
- 06-2022-4326
- Lead agency
- EPA
- Branch
- ECDWE
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- SPCC and/or Federal Response Plan Violations