EPA v. Phillips 66 Pipeline LLC, ACOC
Final Order No Penalty
Case summary
On 10/25/22, EPA Region 6 issued an ACOC under its authority pursuant to RCRA to Phillips 66 located in Sulfer LA. The ACOC was issued in response to violations of: 1) Notification Requierments, 2) Failure to Operate within Generator Status 3) Failure to Comply with Manifest Requierments . The ACOC requires Phillips 66 to certify compliance. Phillips 66 must respond to EPA Region 6 within 30 days of the final ACOC.
Defendants (1)
- Phillips 66 Pipeline LLCNamed in settlement
Facilities (3)
CLIFTON RIDGE MARINE TERMINAL
2115 DAVISON RD., SULPHUR, LA, 70665
Registry ID: 110003309063
PHILLIPS 66 PIPELINE LLC - LAKE CHARLES PIPELINE FACILITY
1851 CLIFTON RIDGE RD, SULPHUR, LA, 70665
Registry ID: 110014466327
CLIFTON RIDGE MARINE TERMINAL
2115 DAVISON RD., SULPHUR, LA, 70665
Registry ID: 110003309063
Statutes cited
- RCRA 3002 — Standards Applicable to Generators of Hazardous Waste
- RCRA 3010 — Notification of Hazardous Waste Activity
Enforcement conclusions (1)
Phillips 66 Pipeline LLC, ACOCentered 2022-10-25
Primary law: RCRA
Timeline (4 milestones)
- 2022-10-25Final Order Issued
- 2022-11-15Compliance Achieved
- 2022-11-25Enforcement Action Closed
- 2022-12-21Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3603459002
- Case number
- 06-2022-0953
- Lead agency
- EPA
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- Standards Applicable to Generators of Hazardous Waste
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2022-0953 . Bulk data: ICIS-FEC download summary.