EPA v. Scissortail Energy-Paden Gas Plant-Paden,OK-RMP ESA-FY2021
Final Order With Penalty
Case summary
From January 21-February 4, 2021, an authorized representative of the EPA conducted a compliance inspection of the Respondent facility. Respondent had violated the RMP regulations of 40 CFR 68.73(d)(3) by failing to conduct the proper frequency of inspections and tests for ten piping circuits by incorrectly identifying these piping circuits as Class 2 piping instead of Class 1 piping.
Defendants (1)
- Scissor Tail Energy, LLCNamed in complaintNamed in settlement
Facilities (1)
PETROLINK ENERGY LLC / PADEN PLANT
4 MILES N AND 1 MILE E OF, PADEN, OK, 74860
Registry ID: 110007394676
Statutes cited
- CAA 112[R][7] — Prevention of Accidental Release/Risk Management Plans (RMPs)
Enforcement conclusions (1)
Scissortail Energy-Paden Gas Plant-Paden,OK-RMP ESA-FY2021entered 2021-09-07
Primary law: CAA
Federal penalty: $9,000
Timeline (6 milestones)
- 2021-08-30Complaint Filed/Proposed Order
- 2021-09-07Enforcement Action Closed
- 2021-09-07Air Resolved
- 2021-09-07Compliance Achieved
- 2021-09-07Enforcement Action Data Entered
- 2021-09-07Final Order Issued
Case metadata
- EPA activity ID
- 3602817559
- Case number
- 06-2021-3363
- Lead agency
- EPA
- Branch
- ECDAC
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- Prevention of Accidental Release/Risk Management Plans (RMPs)
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2021-3363 . Bulk data: ICIS-FEC download summary.