EPA v. Harris Co. FWSD No. 51 - AO
Unilateral Administrative Order Without Adjudication
Case summary
On September 1, 2021, EPA Region 6 issued an Administrative Order (AO) under its authority pursuant to Section 309 of the Clean Water Act to Harris County FWSD No. 51 Wastewater Treatment Plant. The AO was issued in response to effluent violations of permit limits. The AO requires the facility to: 1) submit a list of specific actions taken to correct the violations and 2) submit written certification to EPA that the violations have been corrected and the facility is compliant with its permit. The Respondent must respond to EPA Region 6 within thirty (30) days of the effective dated of the AO.
Defendants (1)
- Mr. Billy AllenNamed in complaintNamed in settlement
Facilities (1)
SUB REGIONAL WASTEWATER TREATMENT PLANT
14701 WOODFOREST BLVD., HOUSTON, TX, 77049-4523
Registry ID: 110000762568
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Harris Co. FWSD No. 51 - AOentered 2021-09-01
Primary law: CWA
Timeline (5 milestones)
- 2021-09-01Final Order Issued
- 2021-09-01Complaint Filed/Proposed Order
- 2021-09-02Enforcement Action Data Entered
- 2023-01-23NPDES Closed
- 2023-01-23Enforcement Action Closed
Case metadata
- EPA activity ID
- 3602814216
- Case number
- 06-2021-1774
- Lead agency
- EPA
- Branch
- 6ECDW
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations