EPA v. ETC TX PROCESSING, LTD (KING RANCH GAS PLANT)
Final Order No Penalty
Case summary
The main root cause of these violations are the incorrect calculations and formulas established in the permit. Final report and explanations will be share with TCEQ and EPA. Facility was not in violation. Currently, the facility is working TCEQ to modify the permit. TCEQ is informed of this situation and we are planning to have a meeting with TCEQ and the facility as part of the transferring files process for this facility case. Violations of BOD5 will still show until the calculations and formulas are update.
Defendants (1)
- ETC TX PROCESSING, LTDNamed in complaintNamed in settlement
Facilities (1)
KING RANCH GAS PLANT
LOCATED 6.36 M. SE FROM INT SOUTH US HWY 281, KINGSVILLE, TX, 78363
Registry ID: 110000727580
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
ETC TX PROCESSING, LTD (KING RANCH GAS PLANT)entered 2021-07-06
Primary law: CWA
Timeline (5 milestones)
- 2021-07-06Complaint Filed/Proposed Order
- 2021-07-06Final Order Issued
- 2021-08-19Enforcement Action Data Entered
- 2021-09-01NPDES Closed
- 2021-09-01Enforcement Action Closed
Case metadata
- EPA activity ID
- 3602802116
- Case number
- 06-2021-1750
- Lead agency
- EPA
- Branch
- 6ENW
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2021-1750 . Bulk data: ICIS-FEC download summary.